We received a surprising update today while I was at work…Our builder sent a couple of photos to show us what he has been up to this week. We closed on the construction less than two weeks ago and he received the notice of commencement just this past Monday. I think he was just as ready to get going as we were!!

The first step was completing site prep work. He was anticipating ten loads of dirt being needed for getting the house level with the roadway. It wound up taking 12 total loads to get the job done. At this point, since demolishing the mobile home and removing the trees, there have been 32 loads of dirt brought in for the lot. Forms and footers are next…I anticipate a poured foundation in the next week to ten days!